Mountain Valley Pipeline Project Causes Stream Sediment Impacts

by admin on April 1, 2020

Virginia Tech team studies stream impacts

Federal reviews delay Mountain Valley Pipeline yet again

From an Article by Laurence Hammack, Roanoke Times, March 27, 2020

A winter hiatus in construction of the Mountain Valley Pipeline will last well into the spring. The latest delay came this week, with word that two federal agencies will take another month to review one of several approvals — set aside by legal challenges from environmental groups — that must be restored before work can ramp up on the highly disputed natural gas pipeline.

Thursday, March 26th had been the deadline for the Federal Energy Regulatory Commission and the U.S. Fish and Wildlife Service to finish their reconsideration of the project’s impact on endangered or threatened species of fish and bats.

But in a letter Wednesday to FERC, the Fish and Wildlife Service said the agencies and Mountain Valley had agreed to take another 32 days, pushing the completion date to April 27. It was the third such delay since December, when the review was originally set to be completed.

Despite the slow process with that and two other sets of suspended permits, the joint venture of five energy companies says it still plans to finish the 303-mile pipeline by the end of this year.

“Mountain Valley will continue to work diligently to obtain all necessary permits to complete construction of this vital infrastructure,” company attorney Matthew Eggerding wrote this week in a letter to FERC.

Since work began two years ago on the $5.5 billion project, regulatory agencies in Virginia and West Virginia have cited Mountain Valley for repeatedly violating erosion and sediment control regulations along the pipeline’s 303-mile path.

Other environmental problems, raised in legal challenges by the Sierra Club and other groups, have led to the suspension of three sets of permits: for the buried pipe to pass through the Jefferson National Forest, under more than 1,000 streams and wetlands in the two Virginias, and into the habitat of endangered species without causing them undue harm.

Last October, FERC ordered that all active construction be halted pending a review of a biological opinion, issued by the Fish and Wildlife Service in 2017, that found the pipeline would not significantly jeopardize protected fish and bats.

Candy Darter — Photo of Blue Ridge Outdoor magazine

In asking for another delay this week, the Fish and Wildlife Service said that while “considerable progress” has been made, more time is needed for Mountain Valley to analyze the impact of construction sediment washed by rainfall into steams populated by the Roanoke logperch and the candy darter.

“The additional time is also needed to allow the Service and the applicant to ensure that any additional information needs have been addressed,” field supervisor Cindy Schulz wrote in the letter to FERC.

When construction was halted last year, Mountain Valley was allowed to stabilize some work sites and maintain erosion control over the pipeline’s entire length from northern West Virginia to Chatham, near the North Carolina line.

Attorneys for the Sierra Club, which challenged the biological opinion and a second permit that allowed limited harm to protected species, have argued that the company is continuing active construction in a “steamrolling” attempt to finish the project.

“The measures currently in place are failing to protect endangered species from severe habitat degradation,” attorney Elly Benson wrote in a Nov. 5 letter filed with the 4th U.S. Circuit Court of Appeals.

The appeals court has put on hold a lawsuit filed by the Sierra Club and other environmental groups until the review of the biological opinion is completed. Meanwhile, other agencies are continuing their court-ordered reconsideration of permits for the pipeline to cross the national forest and streams and rivers.

According to Height Capital Markets, an investment banking firm that has been following the project, delaying the endangered species case until April 27 is not expected to change Mountain Valley’s completion goal of late this year.

Leave a Comment

Previous post:

Next post: